NGCP not solely to blame for project delays, DOE admits

Must read

THE Department of Energy (DOE) has admitted that NGCP is not solely responsible for delays in various transmission projects.

Energy Undersecretary Sharon Garin explained that several factors have contributed to these delays, including pending approvals from the Energy Regulatory Commission (ERC) and issues related to rights of way involving landowners and the Department of Environment and Natural Resources (DENR).

“Sa right of way meron pa. There are cases that have pending ERC approval also. It’s a culmination of everything, like sa Panay, there’s an issue with the owner and the DENR,” Undersecretary Sharon Garin said during the hearing of the Committee on Legislative Franchises.

Lawmakers welcomed Garin’s pronouncement, with Philreca Party-List Rep. Presley De Jesus emphasizing that it is unfair to place all the blame on NGCP for the project delays.

“In short, hindi lang ito solely fault ng NGCP, just to make it clear. Ang masama rito, we’re not trying to defend NGCP. We’re trying to level the playing field. Kasi ang dating, kasalanan ng NGCP kung bakit maraming delays,” De Jesus said.

“But straight from the horse’s mouth, sabi mo may problema ERC at may pending pa sa korte,” he added.

De Jesus also stressed the importance of pursuing these transmission projects in order to bring down electricity prices.

“Ano ba ang purpose natin, pababain ang presyo ng kuryente o we just blame one element of the energy family?” he asked.

NGCP, for its part, has committed to submit its explanation regarding the delayed transmission projects.|

- Advertisement -spot_imgspot_imgspot_imgspot_img

More articles

THE applause had not yet faded when Dharlene Gan of Dakila and the Active Vista Center stepped onto the stage, her words sharp and...
How can a seasoned geologist explain climate change to kids and how can kids understand such an intimidating concept? Through a children’s book and an...
The WVSU Cultural Center this Monday afternoon, September 8, was already alive before the program even began. In the lobby, ushers moved briskly, keeping...
- Advertisement -

Latest article

- Advertisement -